Active engagement

At RiskOversight

UES Prewar Combo — Phase 1–2

412 E 74th St, Unit 12A/B · Manhattan. Owner-side oversight on a gut renovation combining two prewar units. Primary pressure points are kitchen allowances, DOB self-cert revisions, and a pending MEP change order package.

GC
Northline Builders
Architect
Hale + Mercer
Construction value
$3.20M
Target close
Nov 18, 2026

Budget

$2.48M

of $3.20M committed

RFIs

12

4 still open

Change orders

$72K

Pending review

Schedule

−9 days

vs baseline

Risk board

6 shown · 3 open · 1 active issues

Severity
Status
Category
RiskTradeSeverityStatusExposure
Kitchen / AppliancesIssueOpen$18–28K
MEPAt RiskOpen$41,860
MillworkAt RiskOpenTime risk / possible accel. premium
Plumbing / DOBAt RiskWatchingSchedule only (est. 5–8 days)
Building / GCOn TrackWatching
Tile / WaterproofingOn TrackResolved